PG&E Gas Line Issues

The gas line install was incredibly expensive – in excess of $30K. Given that menlo park is not going to allow gas in new construction – except for a stove – you may want to consider foregoing a gas hookup completely. For us, the planning and construction of the new line was extremely disruptive, expensive, time consuming and caused serious stress.

Design was more than $10K. This for a single page plan that showed the trench from the main to our new gas meter. This process took 1-2 months.

The gas line trench and install in the street took more than a month and for at least that long there were metal plates over the trench which were messy and disruptive.

Once we had the design we were ready to start. But it was months before we actually broke ground.

PG&E Gas shutoff before demo

PGE has caused major delays in our project. Some could have been much worse. If you are doing new construction in menlo park you or your contractor should be aware of these issues.

For starters, there was a 4 month lead time for the gas disconnect. The demolition could not proceed until we had the shutoff from PGE. Fortunately I had warning about this so had started the ball rolling early, but we were still behind schedule because of waiting for PGE to disconnect the gas.